WAC 468-310-020
Contents of standard prequalification
questionnaire and financial statement. The standard
prequalification questionnaire and financial statement shall
be transmitted to the director of Washington state ferries. The contractor shall provide the following information:
(1) The name, address, phone number, contractor
registration number and type of organization (corporation,
copartnership, individual, etc.) of the contractor seeking
prequalification.
(2) The contract size in dollars and the class or classes
of work for which the contractor seeks prequalification (such
as vessel dry-docking and hull repairs, vessel electrical
repairs, etc.) as enumerated in WAC 468-310-050(6).
(3) Ownership of the contractor and if a corporation, the
name of the parent corporation (if any) and any affiliated
companies or subsidiaries.
(4) An accurate and complete record of the fifteen
largest contracts in excess of ten thousand dollars performed
by the contractor in whole or in part within the preceding
three years both in Washington and elsewhere, including
subcontracts, giving the contract amount, the date completed,
the class of work, the name, address and phone number of the
owner/agency representative, and any liquidated damages
assessed against the contractor by an owner arising out of the
performance of the contract.
(5) The principal officers and key employees showing the
number of years each engaged in the class or classes of work
for which the contractor seeks prequalification. The
department may require resumes of such personnel as deemed
proper for making its determination.
(6) Except as otherwise provided in this section or WAC 468-310-050(8), a contractor requesting prequalification
certification to perform work in excess of ten million dollars
shall submit copies of its audited annual statements for the
previous three years as audited by an independent certified
public accountant which shall include comparative balance
sheets and income statements, a statement of retained
earnings, supporting schedules and notes attached thereto, and
the opinion of the independent auditor. The financial
statement shall not be more than twelve months old when
submitted. Any wholly owned subsidiary corporation may file
the latest consolidated financial statement of its parent
corporation in lieu of a financial statement prepared solely
for such subsidiary providing the financial statement
otherwise meets the requirements of the preceding two
sentences. If a consolidated financial statement is filed on
behalf of a subsidiary corporation, a bid of the subsidiary
corporation will be considered only if there is on file with
the department a letter from the parent corporation
guaranteeing performance by the subsidiary corporation of its
contract with the department of transportation in an amount at
least equal to the amount of the bid. A letter of guarantee
by a parent corporation may cover a specific contract bid by
its subsidiary or all contracts bid by its subsidiary within a
stated period of time.
(7) A list of all major items of equipment to be used in
those classes of work for which prequalification certification
is requested including the original cost, age, location and
condition of such equipment. The schedule shall show whether
the equipment is owned, leased or rented. All major items of
useful equipment should be listed even though fully
depreciated but no obsolete or useless equipment should be
included. In the event the contractor seeks prequalification
certification to perform work on ferry vessels, the schedule
shall also describe plant facilities of the contractor
including shipyards, dry docks, repair facilities and other
plant facilities.
(8) Such other information as may be required by the
prequalification questionnaire.
(9) Notwithstanding the provisions of this section, a
contractor who wishes to prequalify for the department's
procurement of new auto ferries for the Port Townsend/Keystone
ferry route, pursuant to the department's 2008 invitation for
bids, shall submit a reviewed financial statement for at least
one year in the previous three years, plus annual financial
statements for two additional years in the previous three
years. The reviewed financial statement shall be prepared by
an independent certified public accountant which shall include
comparative balance sheets and income statements, a statement
of retained earnings, supporting schedules and notes attached
thereto, and the opinion of the independent auditor. The form
and quantity of financial statements shall be specified in the
department's invitation for bids and is subject to
modification by addendum during the bid process. This
subsection applies in lieu of the form and quantity of audited
financial statements specified in subsection (6) of this
section for the Port Townsend/Keystone vessel procurement
only. It does not replace or modify any other provisions in
this chapter or governing prequalification statutes that
authorize the department to evaluate a contractor's financial
ability to perform the contract.
[Statutory Authority: RCW 47.56.780, 47.60.680, and 47.60.690. 08-19-004, § 468-310-020, filed 9/4/08, effective
10/5/08. Statutory Authority: RCW 47.60.816. 04-11-004, §
468-310-020, filed 5/5/04, effective 6/5/04. Statutory
Authority: RCW 47.60.680 and 47.60.690. 99-03-025 (Order
189), § 468-310-020, filed 1/11/99, effective 2/11/99. Statutory Authority: RCW 47.60.680. 88-19-040 (Order 114), §
468-310-020, filed 9/14/88. Statutory Authority: 1983 c 133.
83-19-014 (Order 84), § 468-310-020, filed 9/12/83.]