WAC 468-52-050
Application of access control classification
system standards. (1) Review of permits on classified highway
segments. Connection permit applications on controlled access
facilities of the state highway system received on a particular
segment that has been classified in accordance with this chapter
shall be reviewed subject to the requirements of this chapter in
compliance with the permit application process specified in
chapter 468-51 WAC.
(2) Prior approvals. Connections permitted prior to the
adoption of this chapter and unpermitted connections that do not
require closure in accordance with WAC 468-51-030 are not
required to meet the interim standards or the standards of
assigned access classifications adopted in compliance with this
chapter.
(3) New permits required by chapter 468-51 WAC. All new
connection permits required due to significant changes in
property site use in compliance with WAC 468-51-110, or permit
modification in compliance with WAC 468-51-120 shall be reviewed
subject to the requirements of this chapter.
(4) Permits approved under interim standards. Connection
permits that were issued in accordance with the interim standards
in WAC 468-52-040 on a highway segment where an access
classification had not been adopted shall remain in effect after
adoption of an access classification on that highway segment
unless a new permit is required due to changes in property site
use in compliance with WAC 468-51-110 or unless permit
modification, revocation, or closure of the permitted connection
is required in compliance with WAC 468-51-120.
(5) Nonconforming permits. Nonconforming permits may be
issued in accordance with WAC 468-51-100 for certain connections
not meeting the interim standards in WAC 468-52-040 or the access
classification location and spacing standards adopted for a
particular highway segment.
(6) Variance permits. Variance permits may be issued in
accordance with WAC 468-51-105 for certain connections not
meeting the access classification standards for location, spacing
or exceed the number of connections allowed by the standards
adopted for a particular highway segment. These permits may be
allowed if conditions warrant and are demonstrated to the
satisfaction of the department by a traffic analysis, signed and
sealed by a qualified professional engineer who is registered in
accordance with chapter 18.43 RCW, and included in the connection
permit application, and will remain in effect unless a new permit
is required due to changes in property site use in compliance
with WAC 468-51-110 or unless permit modification, revocation, or
closure of the permitted connection is required in compliance
with WAC 468-51-120.
[Statutory Authority: Chapter 47.50 RCW. 99-06-035 (Order 188),
§ 468-52-050, filed 2/25/99, effective 3/28/99. Statutory
Authority: RCW 47.01.101 and chapter 47.50 RCW. 93-03-033
(Order 135), § 468-52-050, filed 1/13/93, effective 2/13/93.]