WAC 468-51-140
Department construction projects. During
construction of department projects, connections will be provided
as replacements for existing approved permitted connections, that
are consistent with all current department spacing, location, and
design standards, based on the following conditions:
(1) Nonconforming connections. All nonconforming
connections will be examined to determine if the construction
project will require relocation, alteration, or closure of the
connection to make it conforming.
(2) Application of current standards. The number and
location of connections shall be modified to the maximum extent
possible to meet current department spacing, location, and design
standards. Where current department standards cannot be met, the
connection shall be classified as nonconforming.
(3) New connections, modifications. The department shall
allow new or require modification of existing connections if a
connection permit application is made and approved.
(4) Replacement of existing connections. When connections
are made as part of a department construction project replacing
existing connection points without material differences, no
additional permit shall be required. Costs shall be borne by the
department.
(5) New connections -- Cost. The construction of new
connection points, if approved by the department, shall be done
at the owner's expense by either the department's contractor as
part of the roadway improvement or by the owner's contractor at
the department's option.
(6) Modifications -- Cost. If the modification of the
connection point, that are based on the owner's request, is more
extensive than the routine replacement of an existing connection,
the owner shall also participate in the differential cost.
(7) Work by permit holder's contractor. The department
shall require that work done by the owner's contractor be
accomplished at the completion of the department's contract or be
scheduled so as not to interfere with the department's
contractor. The department may require a surety bond prior to
construction of the connection in accordance with WAC 468-51-070.
When the number, location or design of existing access
connections to the state highway are being modified by a
department construction project, the resulting modified access
connections shall provide the same general functionality for the
existing property use as they did before the modification, taking
into consideration the existing site design, normal vehicle
types, and traffic circulation requirements.
Notification. The department shall notify affected property
owners, permit holders, business owners and/or emergency
services, in writing, where appropriate, whenever the
department's work program requires the modification, relocation,
or replacement of their access connections. In addition to
written notification, the department shall facilitate, where
appropriate, a public process which may include, but is not
limited to, public notices, meetings or hearings, and/or
individual meetings. The department shall provide the interested
parties with the standards and principles of access management.
[Statutory Authority: Chapter 47.50 RCW. 99-06-034 (Order 187),
§ 468-51-140, filed 2/25/99, effective 3/28/99. Statutory
Authority: RCW 47.01.101 and chapter 47.50 RCW. 92-14-044, §
468-51-140, filed 6/24/92, effective 7/25/92.]