WAC 468-16-150
Prime contractor performance reports. (1)
Performance reports described in this section, substantially in
the format as that appearing at WAC 468-16-210, will be completed
for prime contractors only for projects valued at one hundred
thousand dollars or more. Each prime contractor's performance
report will be classified as to the primary work class being
rated. This shall be stated in Section I of the report by
listing the major classes of work performed by the contractor
e.g., clearing, grading, surfacing, etc.
(2) Performance will be rated under the following headings:
Administration, management, and supervision; quality of work;
progress of work; and equipment.
(3) The following adjectival ratings are established for
performance reports:
|
(a) Superior |
131-150 |
|
(b) Above standard |
101-130 |
|
(c) Standard |
100 |
|
(d) Below standard |
70-99 |
|
(e) Inadequate |
50-69 |
(4) The performance report shall be used in evaluating a
contractor's prequalification status.
(5) The report shall contain a narrative section which
verbally provides the details substantiating the numerical
rating. The narrative section shall be based upon documentation
prepared during the life of the project, such as the project
engineer's diary, the inspector's daily report and other
pertinent documents. This documentation shall constitute the
major portion of the administrative record to be used for any
hearings or litigation that may arise from the rating process.
(6) The performance report will be prepared and discussion
held with the contractor by the project engineer. The report
will include a numerical rating substantiated by a narrative
report which describes the contractor's typical performance. The
narrative will reference such documents as will substantiate the
given numerical rating.
(7) The report will be endorsed by the region operations
engineer or designated assistant who will provide a copy to the
contractor.
(8) The contractor may appeal the rating to the region
administrator in writing within twenty calendar days of the date
the report is received by the contractor. If the report is not
delivered to the contractor in person, it shall be forwarded by
certified mail with a return receipt requested. The appeal must
set forth the specific basis upon which it has been made.
(9) The region administrator or designated assistant will
review all contractor performance reports after they have been
endorsed and may modify the numerical or narrative rating if such
is deemed appropriate. The contractor will be advised of any
changes made. The region administrator will be required to make
comments thereon only when the contractor's overall performance
rating has been rated inadequate, below standard, or superior.
(10) Performance reports, when completed at region level,
will be submitted to the secretary, Attn: Manager, contractor
prequalification office, not later than forty-five calendar days
following final completion of the project.
(11) The region administrator or designated assistant shall
review the appeal and provide a written response to the
contractor by certified mail (return receipt requested) within
twenty calendar days of its receipt. A copy of the appeal and
the response thereto will be forwarded to the secretary, Attn:
Contractor prequalification office.
(12) The contractor may further appeal to the secretary in
writing setting forth the specific basis for the appeal. The
contractor's appeal shall be made within ten calendar days of the
date of receipt of the region administrator's response. When
making an appeal, the contractor may also present information in
person. The secretary will consider the appeal and respond to it
by certified mail within sixty calendar days of its receipt. This determination shall be the final administrative act of the
department.
(13) All prime contractor performance reports shall be
reviewed by the office of the secretary for completeness,
objectivity, and substantiation of numerical ratings. The
secretary may modify the report as deemed appropriate as a result
of the review. The rated contractor and region administrator
shall be given a copy of the modified report. The contractor may
appeal the modified report in the manner and within the time
allotted in subsection (12) of this section to which the
secretary shall respond as cited therein.
(14) A prime contractor performance report shall be
considered a preliminary paper until all reviews and appeals have
been accomplished and it shall have been stamped and initialed
as having been "filed in the office of the secretary."
(15) DOT Form 421-010 is authorized.
[Statutory Authority: RCW 47.01.101, 47.28.030, and 47.28.070. 00-14-055, § 468-16-150, filed 7/3/00, effective 8/3/00;
97-09-045 (Order 168), § 468-16-150, filed 4/15/97, effective
5/16/97; 94-05-004, § 468-16-150, filed 2/2/94, effective 3/5/94;
93-03-020 (Order 134), § 468-16-150, filed 1/12/93, effective
2/12/93; 91-04-014 (Order 128), § 468-16-150, filed 1/28/91,
effective 2/28/91.]