WAC 463-85-120
Greenhouse gases emissions performance
standard applicability. (1) This rule is applicable to all
baseload electric generation facilities and units and baseload
electric cogeneration facilities and units that:
(a) Are new and are permitted for construction and
operation after June 30, 2008, and that utilize fossil fuel or
nonrenewable fuels for all or part of their fuel requirements.
(b) Are existing and that commence operation on or before
June 30, 2008, when the facility or unit's owner or operator
engages in an action listed in subsection (3) or (4) of this
section.
(2) This rule is not applicable to any baseload electric
generation facility or unit or baseload electric cogeneration
facility or unit that is designed and intended to utilize a
renewable fuel to provide at least ninety percent of its total
annual heat input.
(3) A baseload electric generation facility or an
individual electric generating unit at a baseload electric
generation facility is required to meet the emissions
performance standard in effect when:
(a) The new baseload electric generation facility or new
electric generating unit at an existing baseload electric
generation facility is issued a notice of construction
approval or a site certification agreement;
(b) The existing facility or a unit is upgraded; or
(c) The existing facility or a unit is subject to a new
baseload electric long-term financial commitment.
(4) A baseload electric cogeneration facility or unit is
required to meet the emissions performance standard in effect
when:
(a) The new baseload electric cogeneration facility or
new baseload electric cogeneration unit is issued a notice of
construction approval or a site certification agreement;
(b) The existing facility or unit is upgraded; or
(c) The existing facility or unit is subject to a change
in ownership.
(5) A new baseload electric generation facility or unit
or new baseload electric cogeneration facility or unit becomes
an existing baseload electric generation facility or unit or
baseload electric cogeneration facility or unit the day it
commences commercial operation.
[Statutory Authority: Chapters 80.70 and 80.80 RCW and RCW 80.50.040. 08-14-064, § 463-85-120, filed 6/25/08, effective
7/26/08.]