WAC 463-72-040
Initial site restoration plan. (1) At
least ninety days prior to the beginning of site preparation,
the certificate holder shall provide the council with an
initial site restoration plan which addresses site restoration
occurring at the conclusion of the plant's operating life, or
in the event the project is suspended or terminated during
construction or before it has completed its useful operating
life.
(2) The plan shall parallel a decommissioning plan, if
such a plan is prepared for the project.
(3) The initial site restoration plan shall be prepared
in sufficient detail to identify, evaluate, and resolve all
major environmental and public health and safety issues
presently anticipated. It shall describe the process used to
evaluate the options and select measures that will be taken to
restore or preserve the site or otherwise protect all segments
of the public against risks or danger resulting from the site.
The plan shall include a discussion of economic factors
regarding the costs and benefits of various restoration
options versus the relative public risk and shall address
provisions for funding or bonding arrangements to meet the
site restoration or management costs. The provision of
financial assurances shall include evidence of pollution
liability insurance coverage in an amount justified for the
project, and a site closure bond, sinking fund, or other
financial instrument or security in an amount justified in the
plan.
[Statutory Authority: RCW 80.50.040 (1) and (12). 04-21-013,
§ 463-72-040, filed 10/11/04, effective 11/11/04.]