WAC 463-68-070
Review of changes. Under WAC 463-68-060,
construction may start, or restart if construction has been
suspended, only upon the council finding that no changes or
amendments to the site certification agreement, regulatory
permits, or project-related environmental documents are
necessary or appropriate, or upon the council's approval of
any necessary or appropriate changes or amendments. The
council may retain an independent consultant, at the
certificate holder's expense, to evaluate and make
recommendations about whether changes to the site
certification agreement, regulatory permits, or
project-related environmental documents are necessary or
appropriate. This work may include, but is not limited to,
verification of project-related environmental conditions,
regulatory requirements, or appropriate technology.
[Statutory Authority: RCW 80.50.040 (1) and (12). 04-21-013,
§ 463-68-070, filed 10/11/04, effective 11/11/04.]