WAC 332-41-421
EIS preparation under DNR direction. DNR
normally requires a proponent to prepare or help prepare
draft, final, and supplemental EISs at the proponent's
expense. An outside consultant may be used to complete an EIS
only if DNR and the proponent mutually agree upon the
consultant. Any proponent or consultant preparing an EIS
shall do so under DNR's direction.
[Statutory Authority: Chapters 43.21C, 34.05 RCW, WAC 197-11-902(2), [197-11]-904(1) and delegation order, November
5, 2001, signature authority to adopt rules. 07-08-021, §
332-41-421, filed 3/27/07, effective 4/27/07.]