WAC 296-835-13015
Meet specific requirements if you use a flow coating process.
You must:
(1) Make sure all piping is substantial and rigidly supported.
(2) Make sure the paint is supplied by a:
• Gravity tank that does not hold more than ten gallons (38 L)
OR
• Direct low-pressure pumping system.
(3) Have an approved heat-actuated device that shuts down the pumping system if there is a fire.
Note:
The area of the sump, and any areas on which paint flows, should be included in the area of dip tank.