WAC 296-826-30060
Reinstallation.
You must:
• Make sure moved and reinstalled containers of a size to
require field fabrication are reconstructed and reinspected
to:
– Meet the original Unfired Pressure Vessel Code under
which the tank was manufactured and do the following according
to the same code:
▪ A pressure retest
▪ Any necessary rerating.
[Statutory Authority: RCW 49.17.010, 49.17.040, 49.17.050,
49.17.060. 06-10-067, § 296-826-30060, filed 5/2/06,
effective 9/1/06.]