WAC 296-304-10003
Ship's piping systems. Before work is
performed on a valve, fitting, or section of piping in a
piping system where employees may be subject to injury from
the direct escape of steam, or water, oil, or other medium at
a high temperature, the employer shall insure that the
following steps are taken:
(1) The isolation and shutoff valves connecting the dead
system with the live system or systems shall be secured,
blanked, and tagged indicating that employees are working on
the systems. This tag shall not be removed nor the valves
unblanked until it is determined that this may be done without
creating a hazard to the employees working on the system, or
until the work on the system is completed. Where valves are
welded instead of bolted at least two isolation and shutoff
valves connecting the dead system with the live system or
systems shall be secured, locked, and tagged.
(2) Drain connections to the atmosphere on all of the
dead interconnecting systems shall be opened for visual
observation of drainage.
[Statutory Authority: RCW 49.17.010, 49.17.040, 49.17.050,
and 49.17.060. 03-04-099, § 296-304-10003, filed 2/4/03,
effective 8/1/03; Order 74-25, § 296-304-10003, filed 5/7/74.]