WAC 296-155-54900
Crane or derrick requirements for
personnel lifting. (1) Cranes and derricks must meet the
requirements in this part and the applicable crane/derrick
ASME B30 volume in addition to the following requirements in
this section.
(2) The following cranes/derricks must not be used to
lift personnel:
(a) Articulating boom cranes, unless approved by the
manufacturer;
(b) Cranes or derricks with pendant supported, jib type
boom extensions without positive stops.
(3) The crane or derrick being used to hoist the
personnel platform must meet the following requirements:
(a) Live boom or live load capabilities allowing free
fall are removed for the period of personnel lifting;
(b) An operational anti two-block device or upper travel
limit switch is installed on the hoisting systems;
(c) On cranes and derricks with variable angle booms
there is a boom angle indicator that is clearly visible to the
operator;
(d) Equipped with a boom hoist limiting device;
(e) Cranes with a luffing jib must be equipped with:
(i) A jib angle indicator, readily visible to the
operator.
(ii) A jib hoist limiting device.
(f) Cranes with telescoping booms must have a boom length
indicator, readable from the operator's station;
(g) Articulating cranes must be equipped with a properly
functioning automatic overload protection device. Using
articulating boom cranes with suspended platforms is not
allowed. The use of attached work platforms to the
articulating boom crane must be approved by the crane
manufacturer;
(h) Has automatic brakes on the crane/derrick, so motions
stop when the operating controls are released;
(i) Has a holding device, such as a load hold check
valve, that will prevent uncontrolled movement of the
crane/derrick if a system fails, on hydraulic or pneumatic
systems;
(j) Has a way to prevent hydraulic or pneumatic
outriggers or stabilizers, if these are a part of the
crane/derrick, from retracting if the hydraulic or pneumatic
line fails;
(k) The load line hoist drum must have a system, other
than the load line hoist brake, which regulates the lowering
rate of speed of the hoist mechanism. This system or device
must be used when hoisting personnel;
(l) Proper operation required. Personnel hoisting
operations must not begin unless the devices listed in this
section are in proper working order. If a device stops
working properly during such operations, the operator must
safely stop operations. Personnel hoisting operations must
not resume until the device is again working properly.
Alternative measures are not permitted.
(4) Direct attachment of a personnel platform to a
luffing jib is prohibited.
(5) The base of the crane must be level in accordance
with manufacturer's recommendations and in no case greater
than one percent of level. The crane must be located on firm
footing and a qualified person must determine that the footing
is sufficiently firm and stable. Outriggers or stabilizers
must be extended, blocked and locked according to
manufacturer's recommendations, if the crane is equipped with
them, the amount of the extension must be the same for all
outriggers or stabilizers.
(6) The total weight of the lifted load, including
rigging, platform, personnel, tools, and material must not
exceed fifty percent of the crane's rated capacity for the
radius and configuration, under the planned conditions of
operations (except during testing as outlined in WAC 296-155-551).
(7) When the occupied personnel platform is in a
stationary working position, the load and boom hoist brakes,
swing brakes, and operator actuated secondary braking and
locking features (such as pawls or dogs) or automatic
secondary brakes must be engaged.
(8) The area must be inspected where the crane/derrick
will be set up and look for:
(a) Overhead obstructions;
(b) Electrical lines;
(c) Hazardous locations;
(d) Inadequate surface area;
(e) Inadequate support to withstand all force imposed,
wind, weather, and unstable conditions; and
(f) Other potentially hazardous conditions.
(9) Hooks on headache ball assemblies, lower load blocks,
or other attachment assemblies must be of a type that can be
closed and locked, eliminating the hook throat opening.
Alternatively, an alloy anchor type shackle with a bolt, nut
and retaining pin may be used.
[Statutory Authority: RCW 49.17.010, 49.17.040, 49.17.050,
49.17.440, 49.17.060, and 29 C.F.R. 1926, Subpart CC. 12-01-086, § 296-155-54900, filed 12/20/11, effective 2/1/12.]