WAC 296-150F-0350   What must the test procedures and results for design plans include?  (1) Tests to a design for a factory-built home or commercial structure must be witnessed by a professional engineer or architect licensed in Washington state.

     (2) Test reports must contain the following items:

     (a) A description of the methods or standards that applied to the test;

     (b) Drawings and a description of the item tested;

     (c) A description of the test setup;

     (d) The procedure used to verify the correct load;

     (e) The procedure used to measure each condition;

     (f) Test data, including applicable graphs and observations of the characteristics and behavior of the item tested; and

     (g) Analysis, comments, and conclusion.

     (3) The written test procedures, results and conclusions must reference the applicable design plan.