WAC 296-104-302
Installation -- What fuel controls are required on automatically fired boilers
after December 1998? In addition to those requirements listed
in WAC 296-104-301, the following are also required with
regard to installations or refits of gas, oil, or combinations
of gas or oil:
(1) All boilers installed or refitted after December
1998, shall be equipped with suitable primary (flame safeguards)
safety controls, safety limit switches, and burners or
electrical elements as required by a nationally or
internationally recognized standard.
(2) The symbol of
the certifying organization that has investigated such
equipment as having complied with a nationally or
internationally recognized standard shall be affixed to the
equipment and shall be considered evidence that the unit was
manufactured in accordance with that standard. A certifying
organization is one that provides uniform testing,
examination, and listing procedures under established,
nationally or internationally recognized standards, and that
is acceptable to the authorities having jurisdiction.
(3) These devices shall be installed in accordance with
jurisdictional requirements, manufacturer's recommendations,
and/or industry standards as applicable.
[Statutory Authority: RCW 70.79.030, 70.79.040, 70.79.150,
70.79.290, 70.79.330, and 70.79.350. 08-24-072, §
296-104-302, filed 12/1/08, effective 1/1/09; 05-22-092, §
296-104-302, filed 11/1/05, effective 1/1/06. Statutory
Authority: Chapter 70.79 RCW. 04-21-069, § 296-104-302,
filed 10/19/04, effective 1/1/05.]