WAC 296-104-160
Inspection -- What happens if a boiler or
unfired pressure vessel is improperly prepared for inspection? If a boiler or unfired pressure vessel has not been properly
prepared for an internal inspection, or the owner or user fails
to comply with the requirements for hydrostatic test as set forth
in these rules, the inspector may decline to make the inspection
or test and the certificate of inspection shall be withheld until
the owner or user complies with the requirements.
[Statutory Authority: RCW 70.79.030 and 70.79.040. 99-22-026, §
296-104-160, filed 10/26/99, effective 11/26/99; 95-19-058, §
296-104-160, filed 9/15/95, effective 10/16/95; Part III, § 13,
filed 3/23/60.]