WAC 296-104-105
Inspection -- How much time is required
for notification of an internal inspection? Seven days will
be considered sufficient notification. The owner or user
shall prepare each boiler and unfired pressure vessel for
internal inspection and shall prepare for and apply a
hydrostatic pressure test whenever necessary on the date
specified by the inspector.
[Statutory Authority: RCW 70.79.030, 70.79.040, 70.79.150,
70.79.290, 70.79.330, and 70.79.350. 08-24-072, §
296-104-105, filed 12/1/08, effective 1/1/09. Statutory
Authority: RCW 70.79.030 and 70.79.040. 99-22-026, §
296-104-105, filed 10/26/99, effective 11/26/99; 95-19-058, §
296-104-105, filed 9/15/95, effective 10/16/95; Part III, § 2,
filed 3/23/60.]