WAC 296-79-29001
Digester valves and piping. (1) The blow valve of a digester must be
arranged so as to be operated from another room, remote from
safety valves.
(2) Heavy duty pipe, valves, and fittings must be used
between the digester and blow pit, blowtanks and dumptanks. These valves, fittings, and pipes must be inspected at least
semiannually to determine the degree of deterioration and should
be replaced when necessary.
(3) Digester blow valves or controls must be pinned or
locked in closed position throughout the entire cooking period.
(4) Test holes in blow lines of piping systems must not be
covered with insulation or other materials.
[Statutory Authority: RCW 49.17.010, [49.17].040 and[49.17].050
. 99-16-083, § 296-79-29001, filed 8/3/99, effective
11/3/99; Order 74-24, § 296-79-29001, filed 5/6/74.]