WAC 296-46B-590
Special occupancies -- Temporary
installations.
001 Temporary installations.
(1) For the purposes of this section, any circuit used
for construction purposes is considered to be temporary.
003 Temporary installations - time constraints.
(2) Temporary construction service equipment may only be
used for construction purposes and must be disconnected when
the permanent service is connected unless the department
grants an extension of time.
004 Temporary installations - splices.
(3) A splice or junction box is required for all wiring
splice or junction connections in a temporary installation.
[Statutory Authority: RCW 19.28.006, 19.28.010, 19.28.031,
19.28.041, 19.28.061, 19.28.101, 19.28.131, 19.28.161,
19.28.171, 19.28.191, 19.28.201, 19.28.211, 19.28.241,
19.28.251, 19.28.281, 19.28.311, 19.28.321, 19.28.400,
19.28.420, 19.28.490, 19.28.551. 08-24-048, § 296-46B-590,
filed 11/25/08, effective 12/31/08; 05-10-024, § 296-46B-590,
filed 4/26/05, effective 6/30/05.]