WAC 296-46B-517
Special occupancies -- Health care
facilities.
001 Health care facilities.
In health care facilities, the following methods must be
used to determine adequate capacity and ratings of equipment
providing electrical power for the essential electrical
systems defined in Article 517 NEC:
(1) Systems in new facilities:
(a) Emergency system: The emergency branch must consist
of two branches known as:
(i) Life safety system: The feeder conductors and
equipment used to supply electrical power to the life safety
branch must be determined by summation of the connected loads
as determined by Article 220 NEC and may not be subjected to
any reduction due to the diversity of the loads. Feeder and
equipment will be subject to a one hundred twenty-five percent
multiplier for continuous loads in accordance with Article 220
NEC.
(ii) Critical branch system: The feeder conductors and
equipment must be calculated in accordance with Article 220
NEC, including a level of diversity as determined by such
article.
(b) Equipment branch: The feeder conductors and
equipment used to supply electrical power to the equipment
branch of the essential electrical system must be calculated
in accordance with Article 220 NEC, including a level of
diversity as determined by such article.
(c) Generator sizing: The rating of the generator(s)
supplying electrical power to the essential system of a health
care facility must meet or exceed the summation of the loads
determined in (a) and (b) of this subsection with no
additional demand factors applied. Momentary X-ray loads may
be ignored if the generator is rated at least three hundred
percent of the largest momentary X-ray load connected.
(2) Existing essential systems in facilities to which
additional load is to be added:
(a) Existing loads: The existing loads of the separate
branches of the essential electrical system may be determined
by WAC 296-46B-900 (3)(j).
(b) Added loads: Added loads to the separate branches of
the essential electrical system must be determined by
subsection (1) of this section.
(c) Generator sizing: The rating of the generator(s)
supplying electrical power to the essential electrical system
must meet or exceed the summation of the loads determined by
(a) and (b) of this subsection with no additional demand
factors applied.
[Statutory Authority: RCW 19.28.006, 19.28.010, 19.28.031,
19.28.041, 19.28.061, 19.28.101, 19.28.131, 19.28.161,
19.28.171, 19.28.191, 19.28.201, 19.28.211, 19.28.241,
19.28.251, 19.28.281, 19.28.311, 19.28.321, 19.28.400,
19.28.420, 19.28.490, 19.28.551. 08-24-048, § 296-46B-517,
filed 11/25/08, effective 12/31/08; 06-24-041, § 296-46B-517,
filed 11/30/06, effective 12/31/06. Statutory Authority: RCW 19.28.006, 19.28.010, 19.28.031, 19.28.041, 19.28.061,
19.28.101, 19.28.131, 19.28.161, 19.28.171, 19.28.191,
19.28.201, 19.28.211, 19.28.241, 19.28.251, 19.28.271,
19.28.311, 19.28.321, 19.28.400, 19.28.420, 19.28.490,
19.28.551, 2002 c 249, chapters 34.05 and 19.28 RCW. 03-09-111, § 296-46B-517, filed 4/22/03, effective 5/23/03.]