WAC 296-46B-215
Wiring and protection -- Feeders.
005 Diagrams of feeders.
(1) Other than plan review projects, the installer must
provide a one-line diagram showing the service and feeder
details for the project before the initial inspection can be
approved for all nondwelling services or feeders:
(a) Larger than 400 amperes; or
(b) Over 600 volts.
The diagram must be signed and dated by the project owner
if the owner is doing the work, or the assigned administrator
or master electrician if an electrical contractor is doing the
work. The diagram must show:
(c) All services including: Wire size(s), wire type(s),
service size(s) (e.g., voltage, phase, ampacity), overcurrent
protection, available symmetrical fault current at the service
point, equipment short-circuit rating, total load before and
after demand factors have been applied including any demand
factors used, and a panel schedule where multiple
disconnecting devices are present; and
(d) All feeders including: Wire size(s), wire type(s),
feeder size(s) (e.g., voltage, phase, ampacity), overcurrent
protection, total calculated load before and after demand
factors have been applied including any demand factors used,
and a panel schedule(s) where multiple disconnecting devices
are present.
If the installer deviates, in any way, from the
service/feeder design shown on the diagram, a supplemental
diagram must be supplied to the inspector showing the most
recent design before inspection can proceed. Load reductions
and moving branch circuit locations within a panelboard do not
require a supplemental diagram. Written documentation must
also be provided to the inspector that the supplemental
diagram was provided to the project owner at the time of
submission to the inspector.
010 Ground fault protection testing.
(2) Equipment ground fault protection systems required by
the NEC must be tested prior to being placed into service to
verify proper installation and operation of the system as
determined by the manufacturer's published instructions. This
test or a subsequent test must include all system feeders. A
firm having qualified personnel and proper equipment must
perform the tests required. A copy of the manufacturer's
performance testing instructions and a written performance
acceptance test record signed by the person performing the
test must be provided for the inspector's records at the time
of inspection. The performance acceptance test record must
include test details including, but not limited to, all trip
settings and measurements taken during the test.
[Statutory Authority: RCW 19.28.006, 19.28.010, 19.28.031,
19.28.041, 19.28.061, 19.28.101, 19.28.131, 19.28.161,
19.28.171, 19.28.191, 19.28.201, 19.28.211, 19.28.241,
19.28.251, 19.28.281, 19.28.311, 19.28.321, 19.28.400,
19.28.420, 19.28.490, 19.28.551. 08-24-048, § 296-46B-215,
filed 11/25/08, effective 12/31/08. Statutory Authority: RCW 19.28.006, 19.28.010, 19.28.031, 19.28.041, 19.28.061,
19.28.101, 19.28.131, 19.28.161, 19.28.171, 19.28.191,
19.28.201, 19.28.211, 19.28.241, 19.28.251, 19.28.271,
19.28.311, 19.28.321, 19.28.400, 19.28.420, 19.28.490,
19.28.551, 2002 c 249, chapters 34.05 and 19.28 RCW. 03-09-111, § 296-46B-215, filed 4/22/03, effective 5/23/03.]