WAC 296-45-17545
Temporary removal of lockout/tagout. If
the lockout or tagout devices must be temporarily removed from
energy isolating devices and the machine or equipment must be
energized to test or position the machine, equipment, or
component thereof, the following sequence of actions shall be
followed:
(1) Clear the machine or equipment of tools and materials in
accordance with this section;
(2) Remove employees from the machine or equipment area in
accordance with this section;
(3) Remove the lockout or tagout devices as specified in
this section;
(4) Energize and proceed with the testing or positioning;
and
(5) De-energize all systems and reapply energy control
measures in accordance with this section to continue the
servicing or maintenance.
[Statutory Authority: RCW 49.17.010, [49.17].040, [49.17].050
and [49.17].060. 98-07-009, § 296-45-17545, filed 3/6/98,
effective 5/6/98.]