WAC 296-24-31003
Piped systems. (1) Employers must
comply with Chapter 9 (Acetylene Piping) of NFPA 51A-2006
(Standard for Acetylene Charging Plants) (National Fire
Protection Association, 2006 ed., 2006).
(2) When employers can demonstrate that the facilities,
equipment, structures, or installations used to generate
acetylene or to charge (fill) acetylene cylinders were
installed prior to February 16, 2006, these employers may
comply with the provisions of Chapter 7 (Acetylene Piping) of
NFPA 51A-2001 (Standard for Acetylene Charging Plants)
(National Fire Protection Association, 2001 ed., 2001).
(3) The provisions of subsection (2) of this section also
apply when the facilities, equipment, structures, or
installations used to generate acetylene or to charge (fill)
acetylene cylinders were approved for construction or
installation prior to February 16, 2006, but constructed and
installed on or after that date.
Note:
For additional information on acetylene piping systems, see CGA G-1.2-2006, Part 3 (Acetylene Piping) (Compressed Gas
Association, Inc., 3rd ed., 2006).
[Statutory Authority: RCW 49.17.010, 49.17.040, 49.17.050,
49.17.060, and chapter 49.17 RCW. 10-09-089, § 296-24-31003,
filed 4/20/10, effective 7/1/10; Order 73-5, § 296-24-31003,
filed 5/9/73 and Order 73-4, § 296-24-31003, filed 5/7/73.]