WAC 246-359-120
Required inspections. The department or
its designee, when notified by the applicant in writing has
authority to conduct all of the inspections described in this
section.
(1) Site/foundation inspection. To be made after excavations
for footings are complete, and after any required forms and
reinforcing steel are in place, but before any concrete has been
placed.
(2) Concrete slab or under-floor inspection. To be made
after all in-slab or under-floor building service equipment,
conduit, piping accessories and other ancillary equipment items
are in place, but before any concrete is placed or floor
sheathing installed, including the subfloor.
(3) Framing/rough-in inspection. To be made after the roof,
all framing, wall, and roof members are in place including fire
blocking and bracing, heating, and rough electrical and plumbing
has been installed.
(4) Final inspection. To be made after finish grading and
the building is completed and ready for occupancy.
(5) Additional inspections. To be made after the applicant
has received notification that an additional inspection or
inspections are necessary. The department will conduct the
following additional inspections to:
(a) Assure the requirements of this chapter are being met,
specifically to verify:
(i) Stop work orders, WAC 246-359-130, are adhered to;
(ii) Approved plans, according to WAC 246-359-080, have not
been altered without prior department approval; and
(iii) A construction permit has been issued according to WAC 246-359-090;
(b) Determine compliance with other required laws or
ordinances necessary to enforce this chapter; and
(c) Determine if an approved variance is being followed,
when verification cannot be determined through the inspections
described in subsections (1) through (4) of this section.
(6) Special inspections. To be made by a special inspector
when the applicant is building to the alternate construction
standards and the inspections required in subsections (1) through
(5) of this section are not sufficient to determine compliance
with the alternate construction methods.
(7) Reinspections. Reinspections will be conducted and a
reinspection fee charged for each reinspection conducted for the
following reasons:
(a) Work for which an inspection is requested and is not
complete;
(b) Required corrections called for have not been made;
(c) The inspection record card is not posted or readily
available at the worksite;
(d) The approved plans are not readily available to the
inspector; and
(e) The inspector's request for equipment or information was
not provided at the site preventing the inspector from conducting
the scheduled inspection.
[Statutory Authority: RCW 70.114A.081. 99-03-065, §
246-359-120, filed 1/18/99, effective 2/18/99.]