WAC 246-359-080
Plan review approval and expiration of plan
approval. (1) The department will notify the applicant in
writing:
(a) With a "plan review approval letter" when the
construction documents meet the requirements of this chapter; or
(b) With a "not approved letter" when the construction
documents do not meet the requirements of this chapter and a
resubmission of plans or documents is required by the department
for approval.
(2) The applicant has a period of one year from the date of
the plan review approval letter to submit the construction permit
fee or the plan review approval will expire.
(3) The department will destroy all construction documents
related to the project when the plan review approval expires.
(4) To renew action on an expired plan review the applicant
must resubmit the construction documents and pay a new plan
review fee to the department as required in WAC 246-359-990.
(5) Construction documents modified after the department
issues approval must be resubmitted for approval with an
additional fee as specified in WAC 246-359-070.
[Statutory Authority: RCW 70.114A.081. 99-03-065, §
246-359-080, filed 1/18/99, effective 2/18/99.]