WAC 246-335-185
Application and approval. (1) A hospice
care center applicant must submit an application and
construction documents under WAC 246-335-195 and provide
documentation of approval from local zoning commissions, fire
departments, and building departments, if applicable, to the
department for review and approval for all construction as
defined in WAC 246-335-015.
(2) A hospice care center applicant must:
(a) Respond in writing when the department requests
additional or corrected construction documents;
(b) Complete construction in accordance with the final
"department approved" documents;
(c) Submit to the department for review any change
orders, addenda or modifications to the construction documents
for review and approval;
(d) Notify the department in writing when construction is
completed;
(e) Submit to the department a copy of the local
jurisdictions' certificate of occupancy; and
(f) Submit 8 1/2 by 11 inch floor plans.
(3) The department shall notify the hospice care center
in writing when:
(a) The construction documents are approved; or
(b) The construction documents are not approved. If the
construction documents are not approved, the department shall
submit a letter to the applicant identifying sections of this
chapter for which a requirement is stated and there is a
deficiency.
(4) A hospice care center applicant must not begin
construction until the construction documents are approved by
the department and the local jurisdictions have issued the
appropriate permits.
[Statutory Authority: Chapter 70.127 RCW. 02-18-026, §
246-335-185, filed 8/23/02, effective 10/1/02.]