WAC 246-320-505
Design, construction review, and
approval of plans. (1) Drawings and specifications for new
construction, excluding minor alterations, must be prepared by
or under the direction of, an architect registered under
chapter 18.08 RCW. The services of a consulting engineer
registered under chapter 18.43 RCW may be used for
the various branches of work where appropriate. The services
of a registered engineer may be used in lieu of the services
of an architect if work involves engineering only.
(2) A hospital will meet the following requirements:
(a) Request and attend a presubmission conference for
projects with a construction value of two hundred fifty
thousand dollars or more. The presubmission conference shall
be scheduled to occur for the review of construction documents
that are no less than fifty percent complete.
(b) Submit construction documents for proposed new
construction to the department for review within ten days of
submission to the local authorities. Compliance with these
standards and regulations does not relieve the hospital of the
need to comply with applicable state and local building and
zoning codes.
(c) The construction documents must include:
(i) A written program containing, but not limited to the
following:
(A) Information concerning services to be provided and
operational methods to be used;
(B) An interim life safety measures plan to ensure the
health and safety of occupants during construction and
installation of finishes.
(C) An infection control risk assessment indicating
appropriate infection control measures, keeping the
surrounding area free of dust and fumes, and ensuring rooms or
areas are well ventilated, unoccupied, and unavailable for use
until free of volatile fumes and odors;
(ii) Drawings and specifications to include coordinated
architectural, mechanical, and electrical work. Each room,
area, and item of fixed equipment and major movable equipment
must be identified on all drawings to demonstrate that the
required facilities for each function are provided; and
(iii) Floor plan of the existing building showing the
alterations and additions, and indicating location of any
service or support areas; and
(iv) Required paths of exit serving the alterations or
additions.
(d) The hospital will respond in writing when the
department requests additional or corrected construction
documents;
(e) Notify the department in writing when construction
has commenced;
(f) Provide the department with a signed form
acknowledging the risks if starting construction before the
plan review has been completed. The acknowledgment of risks
form shall be signed by the:
(i) Architect; and
(ii) Hospital CEO, COO or designee; and
(iii) Hospital facilities director.
(g) Submit to the department for review any addenda or
modifications to the construction documents;
(h) Assure construction is completed in compliance with
the final "department approved" documents. Compliance with
these standards and regulations does not relieve the hospital
of the need to comply with applicable state and local building
and zoning codes. Where differences in interpretations occur,
the hospital will follow the most stringent requirement.
(i) The hospital will allow any necessary inspections for
the verification of compliance with the construction document,
addenda, and modifications.
(j) Notify the department in writing when construction is
completed and include a copy of the local jurisdiction's
approval for occupancy.
(3) The hospital will not begin construction or use any
new or remodeled areas until:
(a) The infection control risk assessment has been
approved by the department;
(b) The interim life safety plan has been approved by the
department;
(c) An acknowledgment of risk form has been submitted to
the department as required by subsection (2)(f) of this
section;
(d) The department has approved construction documents or
granted authorization to begin construction; and
(e) The local jurisdictions have issued a building
permit, when applicable or given approval to occupy.
(4) The department will issue an "authorization to begin
construction" when subsection (3)(a), (b), and (c) are
approved and the presubmission conference is concluded.
[Statutory Authority: Chapter 70.41 RCW. 10-17-120, §
246-320-505, filed 8/18/10, effective 9/18/10; 08-14-023, §
246-320-505, filed 6/20/08, effective 7/21/08. Statutory
Authority: RCW 70.41.030 and 43.70.040. 99-04-052, §
246-320-505, filed 1/28/99, effective 3/10/99.]