WAC 246-294-030
Application and issuance of operating
permits. (1) No person may operate and no owner shall permit
the operation of a Group A water system unless the owner
annually submits an application along with the required fee to
the department and the department has issued an operating
permit to the system owner. Any owner operating a system may
continue to operate until the department takes final action on
granting or denying the operating permit, in accordance with
WAC 246-294-050.
(2) The department shall mail an application to water
systems annually using a schedule that is based on the size
and type of water system.
(3) In addition to the regularly scheduled issuance of
annual operating permits, new or revised operating permits
shall be required when:
(a) The owner of a new Group A system receives all
required department approvals relating to water system
operation (see WAC 246-294-030(4)); or
(b) Ownership of a Group A system changes (see WAC 246-294-060).
(4) The department may also issue a revised operating
permit when there is a change in a systems compliance that
necessitates a change to a different permit category.
(5) New Group A systems shall be sent operating permit
applications at the time construction documents are submitted
to the department for approval. The deadline for submitting
the completed application and full payment to the department
shall be the same date as:
(a) The Construction Completion Report required by WAC 246-290-120(5); or
(b) The existing system as-built approval required by WAC 246-290-140.
(6) Initial and renewal applications shall be based on
information from the most recent WFIs on file with the
department, and sent to owners on an annual basis. In the
case of a SMA, the department will send a complete list of
systems owned, along with the corresponding system
identification numbers. The SMA shall verify the information,
make corrections or additions and then return the list with
the application.
(7) Upon receipt of the application, the owner or other
legally authorized person shall:
(a) Complete portions of the form which need completing;
(b) Ensure that information on the form is accurate;
(c) Sign the form; and
(d) Return the application to the department within
seventy days of the department's mailing date, accompanied by
the applicable fee.
(8) The applicable fee shall be in the form of a check or
money order made payable to the "Department of Health" or
successor organization as designated by the department and
mailed in accordance with the directions on the application.
(9) Systems which do not return operating permit
applications along with the required fee by the deadline
specified on the notice shall:
(a) Not be issued an operating permit; and
(b) Be subject to the enforcement provisions in WAC 246-294-090.
(10) An additional charge of ten percent or twenty-five
dollars, whichever is greater, shall be added to the
applicable fee listed in WAC 246-294-070 if the owner fails to
return the completed application with applicable fee to the
department within seventy days of the department's mailing
date.
(11) The department shall review each submitted
application. Any changes made on the application by the
applicant shall be evaluated by the department and may result
in an update of the system's WFI form, which would be
reflected on the next renewal application.
(12) If after issuing an operating permit, the department
determines that the permit holder has made false statements,
the department may, in addition to taking other actions
provided by law, revise both current and previously granted
permit fee determinations and charge the owner accordingly.
(13) If the department discovers that an owner has been
operating a system without an operating permit and such system
is covered by the requirements of this chapter, the department
may charge the owner an operating permit fee plus permit fees
owed for each year, including late fees, since the effective
date of this chapter.
[Statutory Authority: Chapter 70.119A RCW. 04-06-047, §
246-294-030, filed 3/1/04, effective 4/1/04; 93-03-047 (Order
325), § 246-294-030, filed 1/14/93, effective 2/14/93.]