WAC 246-291-120
Design report approval. (1) Design
reports shall be submitted to the department for written
approval prior to installation of any new water system, or
water system extension or improvement with the following
exceptions:
(a) Installation of valves, fittings, and meters;
(b) Repair of a system component or replacement with a
similar component of the same capacity; and
(c) Maintenance or painting of surfaces not contacting
potable water.
(2) Design reports submitted for approval by owners of
systems required to have a water system plan, will not be
considered for approval unless there is a current approved
water system plan and the plan adequately addresses the
project.
(3) Design reports shall include, at a minimum, the
following:
(a) Alternatives. Verify contacts with other water
system owners as applicable in accordance with WAC 246-291-140(2);
(b) Legal considerations. Identify legal aspects such as
ownership, right of way, sanitary control area, and
restrictive covenants;
(c) Engineering calculations. Describe how the project
complies with the design considerations;
(d) Drawings. Include detailed drawings of each project
component;
(e) Material specifications. List detailed material
specifications for each project component;
(f) Construction specifications. List detailed
construction specifications and assembly techniques for
carrying out the project;
(g) Testing. Identify testing criteria and procedures
for each applicable portion of the project;
(h) Disinfection. Identify specific disinfection
procedures which must conform with American Water Works
Association standards or other standards acceptable by the
department;
(i) Inspection. Identify provisions for inspection of
the installation of each project component. See WAC 246-291-040 for construction reporting requirements; and
(j) Change orders. All changes except for minor field
revisions must be submitted to and approved by the department
in writing.
(4) Approval of design reports shall be in effect for two
years unless the department determines a need to withdraw the
approval. An extension of the approval may be obtained by
submitting a status report and a written schedule for
completion. Extensions may be subject to additional terms and
conditions imposed by the department.
[Statutory Authority: RCW 43.20.050. 94-14-002, §
246-291-120, filed 6/22/94, effective 7/23/94.]