WAC 246-272A-0265
Record drawings. Upon completion of
the new construction, alteration or repair of the OSS, a
complete and detailed record drawing shall be submitted to
both the health officer and the OSS owner that includes at a
minimum the following:
(1) Measurements and directions accurate to +/- 1/2 foot,
unless otherwise determined by the local health officer, to
assure the following parts of the OSS can be easily located:
(a) All sewage tank openings requiring access;
(b) The ends, and all changes in direction, of installed
and found buried pipes and electrical cables that are part of
the OSS; and
(c) Any other OSS component which, in the judgment of the
health officer or the designer, must be accessed for
observation, maintenance, or operation;
(2) Location and dimensions of reserve area;
(3) Record that materials and equipment meet the
specifications contained in the design;
(4) Initial settings of electrical or mechanical devices
that must be known to operate the system in the manner
intended by the designer or installer; and
(5) For proprietary products, manufacturer's standard
product literature, including performance specifications and
maintenance recommendations needed for operation, monitoring,
maintenance or repair of the OSS.