WAC 246-225A-110
Film processing quality assurance. Registrants found in violation of WAC 246-225A-090 (1)(f) or
(2) shall comply with the following quality assurance
requirements for a minimum of three months:
(1) Conduct an acceptable quality assurance program that
includes weekly tests of film processing to include:
(a) Density of test films; and
(b) Action taken when test film density falls below 15
percent of initial reference levels.
(2) Keep a written or computer log of all periodic
quality assurance testing covered in subsection (1) of this
section, including the weekly test films.
[Statutory Authority: RCW 70.98.050 and 70.98.080. 11-19-013, § 246-225A-110, filed 9/7/11, effective 10/8/11;
08-14-074, § 246-225A-110, filed 6/26/08, effective 7/27/08.]