WAC 246-224-0050   When and how do I register?  (1) You must register with the department through submission of a master business license application and appropriate addendum used by MLS no later than fifteen calendar days of initial use unless shielding plans review is required.

     (2) Facilities requiring shielding plan review must register with DOL and submit plans to the department for review prior to construction or installation of radiation machines according to WAC 246-225-030, General requirements -- Plan review.

     (3) Registration is valid for one year from the department approval date, or any other date as may be determined through partnership with MLS.

     (4) Pay applicable registration fees according to WAC 246-254-053, Radiation machine facility registration fees.

     (5) Submit registration information and applicable fees to MLS in accordance with their instructions.


Note: For DOL information, visit the following web site:
http://www.dol.wa.gov/business/xray.htm.




[Statutory Authority: RCW 19.02.050, 43.20B.020, 43.70.110, 70.98.050, and 70.98.080. 08-09-079, § 246-224-0050, filed 4/16/08, effective 5/17/08. Statutory Authority: RCW 70.98.050 and [70.98.]080. 02-14-050, § 246-224-0050, filed 6/27/02, effective 7/28/02.]