WAC 194-37-160
Documentation of financial cost
cap -- Current information and timeline. By January 1 of the
first target year that a utility fulfills its renewable energy
requirements under RCW 19.285.050, the utility shall select
one of the following methodologies for documenting the
incremental cost of all eligible renewable resources acquired
thereafter by that utility:
(1) Annual update methodology. In each year that a
utility fulfills its renewable energy requirements by
complying with the cost cap identified in RCW 19.285.050 it
must document its calculations no later than January 1 of the
target year. The utility will use the most current
information available to the utility within twelve months
prior to the initial documentation of the cost cap pursuant to
WAC 194-37-170 through 194-37-190. The utility will update
this documentation in its June 1 report submitted pursuant to
RCW 19.285.070. These annual updates of costs, based on the
most current information available, apply to both the eligible
renewable resource and the substitute resource.
(2) Permanent one-time methodology. For each new
investment in an eligible renewable resource, a utility shall
perform a one-time calculation of the levelized incremental
cost pursuant to WAC 194-37-170 through 194-37-190. The
levelized incremental cost shall be a single annual value
expressed in real, constant-year dollars. The levelized
incremental cost for each eligible renewable resource project
or purchase, calculated through this one-time analysis in the
year of acquisition, shall be allowed to inflate utilizing the
Producer Price Index over the life of the eligible renewable
resource after the initial calculation. The utility will
include a determination of incremental cost for each new
investment in an eligible renewable resource and
inflation-adjusted incremental costs for previous eligible
renewable resource investments in its June 1 report submitted
pursuant to RCW 19.285.070, beginning in the year the utility
complies with the cost cap identified in RCW 19.285.050.
[Statutory Authority: RCW 19.285.080(2). 08-07-079, §