WAC 194-22-010
Purpose and goal. The purpose of this
chapter is to establish the process by which the state of
Washington and Washington state utilities will initiate and
implement statewide electric load curtailment when there is an
insufficient supply of electric energy. This chapter constitutes
the Washington state curtailment plan for electric energy (plan).
The plan is not intended to be activated for relatively
short-term emergencies such as those caused by extremely cold
weather or the temporary loss of a major generating plant, but
for regional, protracted shortages of electric energy. The plan
will be activated by the department of community, trade, and
economic development for regional emergencies for which regional
curtailment is necessary. Such emergencies may or may not
coincide with other emergencies for which other actions, such as
repair of damaged facilities, are necessary.
The goal of this plan is to accomplish necessary curtailment
while treating consumers fairly and equitably, minimizing adverse
impacts from curtailment, complying with existing state laws and
regulations, and providing for smooth, efficient, and effective
curtailment administration.
[Statutory Authority: RCW 43.21F.045. 99-21-008, § 194-22-010,
filed 10/8/99, effective 11/8/99; 94-20-103, § 194-22-010, filed
10/4/94, effective 11/4/94.]