WAC 173-407-060
Carbon dioxide mitigation plan
requirements and options under Part I. (1) Once the total
carbon dioxide emissions mitigation quantity is calculated,
what is next? The facility must mitigate that level of carbon
dioxide emissions. A CO2 mitigation plan is required and must
be approved as part of the order of approval. RCW 80.70.020
(2)(b) states that "For fossil-fueled thermal electric
generation facilities not under jurisdiction of the council,
the order of approval shall require an approved carbon dioxide
mitigation plan." A mitigation plan is a proposal that
includes the process or means to achieve carbon dioxide
mitigation through use of mitigation projects or carbon
credits (RCW 80.70.010).
(2) What are the mitigation plan options? The options
are identified in RCW 80.70.020(3), which states that "An
applicant for a fossil-fueled thermal electric generation
facility shall include one or a combination of the following
carbon dioxide mitigation options as part of its mitigation
plan:
(a) Payment to a third party to provide mitigation;
(b) Direct purchase of permanent carbon credits; or
(c) Investment in applicant-controlled carbon dioxide
mitigation projects, including combined heat and power
(cogeneration)."
(3) What are the requirements of the payment to a third
party option? The payment to a third party option
requirements are found in RCW 80.70.020 (5) and (6).
Subsection (5) identifies the mitigation rate for this option
and describes the process for changing the mitigation rate.
Subsection (6) describes the payment options.
The initial mitigation rate is $1.60 per metric ton of
carbon dioxide to be mitigated. If there is a cogeneration
plant, the monetary amount is based on the difference between
twenty percent of the total carbon dioxide emissions and the
cogeneration credit. This rate will change when the energy
facility site evaluation council adjusts it through the
process described in RCW 80.70.020 (5)(a) and (b). The total
payment amount = mitigation rate x mitigation quantity.
An applicant may choose between a lump sum payment or
partial payment over a period of five years. The lump sum
payment is described in RCW 80.70.020 (6)(a) and (b). The
payment amount is the mitigation quantity multiplied by the
per ton mitigation rate. The entire payment amount is due to
the independent qualified organization no later than one
hundred twenty days after the start of commercial operation.
The alternative to a one-time payment is a partial
payment described in RCW 80.70.020 (6)(c). Under this
alternative, twenty percent of the total payment is due to the
independent qualified organization no later than one hundred
twenty days after the start of commercial operation. A
payment of the same amount (or an adjusted amount if the rate
is changed under RCW 80.70.020 (5)(a)) is due on the
anniversary date of the initial payment for the next four
consecutive years. In addition, the applicant is required to
provide a letter of credit or comparable security for the
remaining 80% at the time of the first payment. The letter of
credit (or comparable security) must also include possible
rate changes.
(4) What are the requirements of the permanent carbon
credits option? RCW 80.70.030 identifies the criteria and
specifies that these credits cannot be resold without approval
from the local air authority having jurisdiction or ecology
where there is no local air authority. The permanent carbon
credit criteria of RCW 80.70.030(1) are as follows:
(a) Credits must derive from real, verified, permanent,
and enforceable carbon dioxide or carbon dioxide equivalents
emission mitigation not otherwise required by statute,
regulation, or other legal requirements;
(b) The credits must be acquired after July 1, 2004; and
(c) The credits may not have been used for other carbon
dioxide mitigation projects.
(5) What are the requirements for the applicant
controlled mitigation projects option? RCW 80.70.040
identifies the requirements for applicant controlled
mitigation projects. Subsections (1) through (5) specify the
criteria. The direct investment cost of the applicant
controlled mitigation project including funds used for
selection, monitoring, and evaluation of mitigation projects
cannot be required by ecology or the local authority to exceed
the cost of making a lump sum payment to a third party per WAC 173-407-060(3).
The applicant controlled mitigation project must be:
(a) Implemented through mitigation projects conducted
directly by, or under the control of, order of approval
holder.
(b) Approved by the authority having jurisdiction or the
department where there is no local air authority and
incorporated as a condition of the proposed order of approval.
(c) Fully in place within a reasonable time after the
start of commercial operation. Failure to implement an
approved mitigation plan is subject to enforcement under
chapter 70.94 RCW.
(d) The order of approval holder may not use more than
twenty percent of the total funds for the selection,
monitoring, and evaluation of mitigation projects, and the
management and enforcement of contracts.
[Statutory Authority: Chapter 80.80 RCW. 08-14-011 (Order
07-11), § 173-407-060, filed 6/19/08, effective 7/20/08. Statutory Authority: RCW 70.94.892 and chapter 80.70 RCW.
05-01-237 (Order 03-09), § 173-407-060, filed 12/22/04,
effective 1/22/05.]