WAC 173-406-802
Units with repowering extension plans. (1) Design and engineering and contract requirements. No
later than January 1, 2000, the designated representative of a
unit governed by an approved repowering plan shall submit to
the administrator and the permitting authority:
(a) Satisfactory documentation of a preliminary design
and engineering effort.
(b) A binding letter agreement for the executed and
binding contract (or for each in a series of executed and
binding contracts) for the majority of the equipment to
repower the unit using the technology conditionally approved
by the administrator under 40 CFR 72.44 (d)(3).
(c) The letter agreement under (b) of this subsection
shall be signed and dated by each party and specify:
(i) The parties to the contract;
(ii) The date each party executed the contract;
(iii) The unit to which the contract applies;
(iv) A brief list identifying each provision of the
contract;
(v) Any dates to which the parties agree, including
construction completion date;
(vi) The total dollar amount of the contract; and
(vii) A statement that a copy of the contract is on site
at the source and will be submitted upon written request of
the administrator or the permitting authority.
(2) Removal from operation to repower. The designated
representative of a unit governed by an approved repowering
plan shall notify the administrator and the permitting
authority in writing at least sixty days in advance of the
date on which the existing unit is to be removed from
operation so that the qualified repowering technology can be
installed, or is to be replaced by another unit with the
qualified repowering technology, in accordance with the plan.
(3) Commencement of operation. Not later than sixty days
after the units repowered under an approved repowering plan
commences operation at full load, the designated
representative of the unit shall submit a report to the
administrator and the permitting authority, comparing the
actual hourly emissions and percent removal of each pollutant
controlled at the unit to the actual hourly emissions and
percent removal at the existing unit under the plan prior to
repowering, determined in accordance with 40 CFR part 75.
(4) Decision to terminate. If at any time before the end
of the repowering extension and before completion of
construction and start up testing, the owners and operators
decide to terminate good faith efforts to design, construct,
and test the qualified repowering technology on the unit to be
repowered under an approved repowering plan, then the
designated representative shall submit a notice to the
administrator and the permitting authority by the earlier of
the end of the repowering extension or a date within thirty
days of such decision, stating the date on which the decision
was made.
[Statutory Authority: Chapter 70.94 RCW. 94-23-127 (Order
94-23), § 173-406-802, filed 11/23/94, effective 12/24/94.]