WAC 173-406-702   Permit modifications.  (1)(a) Permit modifications shall follow the permit issuance requirements of WAC 173-406-600, 173-401-810 and 173-401-820.

     (b) For purposes of applying (a) of this subsection, a permit modification shall be treated as an acid rain permit application, to the extent consistent with WAC 173-406-700.

     (2) The following permit revisions are permit modifications:

     (a) Relaxation of an excess emission offset requirement after approval of the offset plan by the administrator;

     (b) Incorporation of a final nitrogen oxides alternative emission limitation following a demonstration period;

     (c) Determinations concerning failed repowering projects under WAC 173-406-402 (6)(a)(i) and (b); and

     (d) At the option of the designated representative submitting the permit revision, the permit revisions listed in WAC 173-406-703(2).



[Statutory Authority: Chapter 70.94 RCW. 94-23-127 (Order 94-23), § 173-406-702, filed 11/23/94, effective 12/24/94.]