WAC 173-400-114
Requirements for replacement or
substantial alteration of emission control technology at an
existing stationary source. (1) Any person proposing to
replace or substantially alter the emission control technology
installed on an existing stationary source or emission unit
shall file a notice of construction application with the
appropriate authority, or with ecology in areas or for sources
over which ecology has jurisdiction. Replacement or
substantial alteration of control technology does not include
routine maintenance, repair or similar parts replacement.
(2) For projects not otherwise reviewable under WAC 173-400-110, ecology or the authority may:
(a) Require that the owner or operator employ RACT for
the affected emission unit;
(b) Prescribe reasonable operation and maintenance
conditions for the control equipment; and
(c) Prescribe other requirements as authorized by chapter 70.94 RCW.
(3) Within thirty days of receipt of a notice of
construction application under this section ecology or the
authority shall either notify the applicant in writing that
the application is complete or notify the applicant in writing
of all additional information necessary to complete the
application. Within thirty days of receipt of a complete
notice of construction application under this section ecology
or the authority shall either issue an order of approval or a
proposed RACT determination for the proposed project.
(4) Construction shall not "commence," as defined in WAC 173-400-030, on a project subject to review under this section
until ecology or the authority issues a final order of
approval. However, any notice of construction application
filed under this section shall be deemed to be approved
without conditions if ecology or the authority takes no action
within thirty days of receipt of a complete notice of
construction application.
(5) Approval to replace or substantially alter emission
control technology shall become invalid if construction is not
commenced within eighteen months after receipt of such
approval, if construction is discontinued for a period of
eighteen months or more, or if construction is not completed
within a reasonable time. Ecology or the authority may extend
the eighteen-month period upon a satisfactory showing that an
extension is justified. This provision does not apply to the
time period between construction of the approved phases of a
phased construction project; each phase must commence
construction within eighteen months of the projected and
approved commencement date.
[Statutory Authority: Chapter 70.94 RCW, RCW 70.94.141,[70.94.]152
, [70.94.]331, [70.94.]510 and 43.21A.080. 01-17-062 (Order 99-06), § 173-400-114, filed 8/15/01,
effective 9/15/01. Statutory Authority: Chapter 70.94 RCW. 93-18-007 (Order 93-03), § 173-400-114, filed 8/20/93,
effective 9/20/93.]