WAC 173-350-030
Effective dates. (1) Effective dates.
These standards apply to all facilities, except existing
facilities, upon the effective date of this chapter.
(2) Effective dates - Existing facilities.
(a) The owner or operator of existing facilities shall:
(i) Meet all applicable operating, environmental
monitoring, closure and post-closure planning, and financial
assurance requirements of this chapter within twenty-four
months of the effective date of this chapter; and
(ii) Meet all applicable performance and design
requirements, other than location or setback requirements,
within thirty-six months of the effective date of this
chapter.
(b) These standards apply to all new solid waste handling
units at existing facilities upon the effective date of this
chapter.
(c) The owner or operator of existing facilities shall
initiate the permit modification process outlined in WAC 173-350-710(4) within eighteen months after the effective date
of this chapter. If a permit modification is necessary, every
application for a permit modification shall describe the date
and methods for altering an existing facility to meet (a)(i)
through (iii) of this subsection.
(d) The jurisdictional health department shall determine
if a new permit application is required based on the extent of
the changes needed to bring the facility into compliance.
(e) An existing facility completing closure within twelve
months of the effective date of this chapter may close in
compliance with the requirements of chapter 173-304 WAC,
Minimum functional standards for solid waste handling. Any
facility that does not complete closure within twelve months
of the effective date of this chapter shall close in
compliance with applicable requirements of this chapter.
[Statutory Authority: Chapter 70.95 RCW. 03-03-043 (Order
99-24), § 173-350-030, filed 1/10/03, effective 2/10/03.]