WAC 173-240-180
Approval of construction changes. All
wastewater facilities subject to the provisions of this rule must
be constructed in accordance with the plans and specifications
approved by the department. Any contemplated changes during
construction, which are significant deviations from the approved
plans, must first be submitted to the department for approval.
[Statutory Authority: RCW 90.48.110. 00-15-021 (Order 00-09), §
173-240-180, filed 7/11/00, effective 8/11/00. Statutory
Authority: Chapters 43.21A and 90.48 RCW. 83-23-063 (Order DE
83-30), § 173-240-180, filed 11/16/83. Statutory Authority: RCW 90.48.110. 79-02-033 (Order DE 78-10), § 173-240-180, filed
1/23/79. Formerly chapter 372-20 WAC.]