WAC 173-240-160
Requirement for professional engineer. (1)
All required engineering reports, and plans and specifications
for the construction or modification of wastewater facilities
must be prepared under the supervision of a professional engineer
licensed in accordance with chapter 18.43 RCW. All copies of
these documents submitted to the department for review shall bear
the seal of the professional engineer under whose supervision
they have been prepared.
(2) Upon request of the owner, the department may waive the
above requirement for construction or modification at industrial
wastewater facilities.
[Statutory Authority: RCW 90.48.110. 00-15-021 (Order 00-09), §
173-240-160, filed 7/11/00, effective 8/11/00. Statutory
Authority: Chapters 43.21A and 90.48 RCW. 83-23-063 (Order DE
83-30), § 173-240-160, filed 11/16/83. Statutory Authority: RCW 90.48.110. 79-02-033 (Order DE 78-10), § 173-240-160, filed
1/23/79. Formerly chapter 372-20 WAC.]