WAC 173-240-140
Plans and specifications. (1) Upon request
of the owner the department may, at its discretion, allow
submission of conceptual plans for industrial facilities, as
noted in WAC 173-240-110(5). Two copies of the plans and
specifications must be submitted to the department for approval
before the start of construction.
(2) The plans and specifications shall include the following
information together with any other relevant data as requested by
the department:
(a) Repeat presentation of the basic engineering design
criteria from the engineering report.
(b) If there are any deviations from the concepts of the
engineering report, an explanation of the changes that includes
as much detail as would have been provided in an engineering
report.
(c) The plan and section drawings of major components, such
as the treatment units, pump stations, flow measuring devices,
sludge handling equipment, and influent and effluent piping. Foundations or soil preparation or both should be shown for major
structures.
(d) A general site drawing that shows the location with
respect to the entire plant site and a detailed site drawing that
shows the component siting.
(e) A schematic drawing that shows flows that include: In
plant collection, and wastewater pumping, treatment, and
discharge.
(f) A hydraulic profile that shows head under maximum flows.
This requirement may be waived where the three step submission
of documents has been waived under WAC 173-240-110(5).
(g) Instrumentation, controls, and sampling schematics.
(h) General operating procedures, such as startup, shutdown,
spills, etc.
[Statutory Authority: RCW 90.48.110. 00-15-021 (Order 00-09), §
173-240-140, filed 7/11/00, effective 8/11/00. Statutory
Authority: Chapters 43.21A and 90.48 RCW. 83-23-063 (Order DE
83-30), § 173-240-140, filed 11/16/83. Statutory Authority: RCW 90.48.110. 79-02-033 (Order DE 78-10), § 173-240-140, filed
1/23/79. Formerly chapter 372-20 WAC.]