WAC 173-240-090
Declaration of construction completion. (1) Within thirty days after acceptance by the owner of the
construction or modification of a domestic wastewater facility,
the professional engineer in responsible charge of inspection of
the project shall submit to the department:
(a) One complete set of record drawings or as-builts;
(b) A declaration stating the facilities were constructed in
accordance with the provisions of the construction quality
assurance plan and without significant change from the department
approved plans and specifications.
(2) The declaration will be furnished by the department and
will be the same form as WAC 173-240-095, declaration of
construction of water pollution control facilities. The
submission of the declaration is not necessary for sewer line
extensions where the local government entity has received
approval of a general sewer plan and standard design criteria.
[Statutory Authority: RCW 90.48.110. 00-15-021 (Order 00-09), §
173-240-090, filed 7/11/00, effective 8/11/00. Statutory
Authority: Chapters 43.21A and 90.48 RCW. 83-23-063 (Order DE
83-30), § 173-240-090, filed 11/16/83. Statutory Authority: RCW 90.48.110. 79-02-033 (Order DE 78-10), § 173-240-090, filed
1/23/79. Formerly chapter 372-20 WAC.]