WAC 173-240-075
Construction quality assurance plan. (1)
Before construction a detailed plan must be submitted to the
department that shows how adequate and competent construction
inspection will be provided.
(2) The construction quality assurance plan shall include a:
(a) Construction schedule with a summary of planned
construction activities, their sequence, interrelationships,
durations, and terminations.
(b) Description of the construction management organization,
management procedures, lines of communication, and
responsibility.
(c) Description of anticipated quality control testing that
includes type of test, frequency, and who will perform the tests.
(d) Description of the change order process that includes
who will initiate change orders, as well as who will review,
negotiate, and approve change orders.
(e) Description of the technical records handling
methodology that includes where plans and specifications,
as-built drawings, field orders, and change orders will be kept.
(f) Description of the construction inspection program that
includes inspection responsibility, anticipated inspection
frequency, deficiency resolution, and inspector qualifications.
[Statutory Authority: RCW 90.48.110. 00-15-021 (Order 00-09), §
173-240-075, filed 7/11/00, effective 8/11/00. Statutory
Authority: Chapters 43.21A and 90.48 RCW. 83-23-063 (Order DE
83-30), § 173-240-075, filed 11/16/83.]