WAC 173-182-800   PRC application.  (1) To become a state-approved PRC, a response contractor must:

     (a) Submit an application as set forth in subsection (2) of this section;

     (b) Have a process to provide twenty-four hour/day contact for spill response;

     (c) Commit to begin mobilization efforts immediately upon notification but no later than one hour from notification of a spill;

     (d) Maintain equipment in accordance with manufacturer specifications; and

     (e) Assist plan holders in meeting the requirements for plans and drills in Washington.

     (2) To apply, a contractor should complete, sign and submit the application form number ECY 070-216.



[Statutory Authority: Chapters 88.46, 90.56, and 90.48 RCW. 06-20-035 (Order 00-03), § 173-182-800, filed 9/25/06, effective 10/26/06.]