WAC 173-182-355   Transfer sites for covered vessels at locations where transfers occur, and for facilities with a vessel terminal.  


Time (hours) Boom/Assessment Minimum Oil Recovery Rate

% of WCS volume per 24 hours
Minimum Storage
6 Additional 10,000 feet of boom to be used for containment, recovery or protection could have arrived Capacity to recover the lesser of 10% of worst case spill volume or 12,500 barrels within 24-hour period could have arrived 2 times the EDRC
12 Additional 20,000 feet of boom to be used for containment, recovery or protection could have arrived Capacity to recover the lesser of 15% of worst case spill volume or 36,000 barrels within 24-hour period could have arrived 2 times the EDRC
24 Additional 20,000 feet of boom to be used for containment, recovery or protection could have arrived Capacity to recover the lesser of 20% of worst case spill volume or 48,000 barrels within 24-hour period could have arrived 3 times the EDRC
48 More boom as necessary for containment, recovery or protection Capacity to recover the lesser of 25% of worst case spill volume or 60,000 barrels within 24-hour period could have arrived More as necessary to not slow the response




[Statutory Authority: Chapters 88.46, 90.56, and 90.48 RCW. 06-20-035 (Order 00-03), § 173-182-355, filed 9/25/06, effective 10/26/06.]