WAC 173-182-130   Phase in language.  (1) This section applies to those plan holders who, on the effective date of this chapter, have approved or conditionally approved plans, and response contractors with approved applications.

     (2) For existing approved facility plan holders:

     (a) Plans holders for onshore facilities capable of storing one million gallons or more of oil shall submit a revised contingency plan to ecology six months after the effective date of this chapter; except, plan holders that received plan approval six months prior to the effective date of this chapter must submit a revised plan within twelve months of the effective date of this chapter. In submitting the revised plan, plan holders must include a compliance schedule describing how they will meet the requirements in WAC 173-182-310 through 173-182-440. Plan holders shall have eighteen months from the effective date of this chapter to reach compliance.

     (b) All other onshore facilities shall submit revised plans to ecology within twelve months after the effective date of this chapter; except plan holders that received plan approval six months prior to the effective date of this chapter must submit a revised plan within eighteen months of the effective date of this chapter. In the revised plan, plan holders must include a compliance schedule describing how they will meet the requirements in WAC 173-182-310 through173-182-440 . Plan holders shall have twenty-four months from the effective date of this chapter to reach compliance.

     (3) For existing approved vessel plan holders:

     (a) Plan holders for tank vessels submit a revised contingency plan to ecology six months after the effective date of this chapter; except plan holders that received plan approval six months prior to the effective date of this chapter must submit a revised plan within twelve months of the effective date of this chapter. In the revised plan, plan holders must include a compliance schedule describing how they will meet the requirements in WAC 173-182-310 through173-182-440 . Plan holders shall have eighteen months from the effective date of this chapter to reach compliance.

     (b) All other covered vessels shall submit revised plans to ecology within twelve months after the effective date of this chapter; except plan holders that received plan approval six months prior to the effective date of this chapter must submit a revised plan within eighteen months of the effective date of this chapter. In the revised plan, plan holders must include a compliance schedule describing how they will meet the requirements in WAC 173-182-310 through 173-182-440. Plan holders shall have twenty-four months from the effective date of this chapter to reach compliance.

     (4) PRCs shall submit new applications to ecology within twelve months.



[Statutory Authority: Chapters 88.46, 90.56, and 90.48 RCW. 06-20-035 (Order 00-03), § 173-182-130, filed 9/25/06, effective 10/26/06.]