WAC 173-180-820
Unannounced drills for Class 2
facilities. (1) Ecology will evaluate these drills.
(2) At the start of the unannounced drill, ecology will
notify the Class 2 facility of the drill objectives,
expectations and scenario.
(3) The Class 2 facility may request to be excused from
an unannounced deployment drill if conducting the drill poses
an unreasonable safety or environmental risk, or significant
economic hardship. If ecology approves the request, ecology
will call the drill on another date.
(4) Ecology will provide the facility with a drill
evaluation. If deficiencies are found during the drill,
ecology may require a redrill after the facility corrects the
deficiencies.
[Statutory Authority: RCW 88.46.160, 88.46.165, and chapter 90.56 RCW. 06-20-034 (Order 06-02), § 173-180-820, filed
9/25/06, effective 10/26/06.]