WAC 173-180-760
Class 2 facility -- Response plan update
and timeline. (1) The facility is required to keep the
response plan up-to-date with accurate information.
(2) Whenever changes are made to the response plan, two
paper copies and one electronic of the changed sections must
be submitted to ecology to be placed in the facility's plan on
file at ecology.
(3) Ecology must review the facility's oil transfer
response plan every five years.
(a) The facility must submit two paper copies or one
electronic copy of the response plan for reapproval; or
(b) The facility may submit a letter to ask ecology to
review the response plan that is currently on file at the
agency.
(4) The facility must submit the response plan or letter
at least ninety calendar days in advance of the expiration
date of the response plan.
(5) Ecology may review and request changes to your
response plan following any oil spill, inspection, or drill.
[Statutory Authority: RCW 88.46.160, 88.46.165, and chapter 90.56 RCW. 06-20-034 (Order 06-02), § 173-180-760, filed
9/25/06, effective 10/26/06.]