WAC 173-180-230
Preloading or cargo transfer plan
requirement. Prior to any oil transfer, a transfer plan must
be filled out and discussed between the delivering and
receiving PICs. A facility must not begin a transfer until
this plan has been discussed during the pretransfer conference
described in WAC 173-180-235. The plan must, at a minimum,
include:
(1) Identification, location and capacity of the vessel's
tanks receiving oil;
(2) Level and type of liquid in all bunker or cargo oil
tanks prior to the oil transfer;
(3) Final ullage or innage, and percent of each tank to
be filled;
(4) Sequence in which the tanks are to be filled; and
(5) The facility or vessel's procedures to regularly
monitor all receiving tank levels and valve alignments during
the transfer operation.
[Statutory Authority: RCW 88.46.160, 88.46.165, and chapter 90.56 RCW. 06-20-034 (Order 06-02), § 173-180-230, filed
9/25/06, effective 10/26/06.]