WAC 173-175-140
Plans and specifications. (1) Two
copies of the plans and specifications, bearing the seal and
signature of the project engineer, shall be submitted to the
department for engineering review. Upon approval, one copy
will be retained by the department and the other copy will be
returned to the owner or the project engineer.
(2) For large or complex projects, one copy of the
preliminary or intermediate level plans, in addition to the
final plans, shall be submitted to the department for review.
(3) To be approved, the plans and specifications must
contain sufficient detail to describe the proposed
construction work.
(a) The following items, as a minimum, shall be included
as part of the construction plans:
(i) Project location and vicinity maps;
(ii) Site map of dam, reservoir area, and appurtenances;
(iii) Sectional view along longitudinal axis of dam and
foundation;
(iv) Cross-sectional view of dam at location of maximum
height;
(v) Cross-sectional views and profiles of spillway(s),
outlet facilities, and other appurtenances;
(vi) Steel reinforcement placement and bar sizing for
concrete construction must be shown in at least one section or
profile; and
(vii) The plan for diversion and control of water during
construction.
(b) The following items, as a minimum, shall be included
as part of the construction specifications:
(i) Type, class, or description of all materials to be
used;
(ii) The requirements for fill placement, moisture
conditioning, and minimum level of compaction of all earthen
zones;
(iii) The requirements, procedures, and minimum standards
for concrete construction and/or structural details.
[Statutory Authority: RCW 43.21A.064, [43.21A.]080 and86.16.061
. 92-12-055 (Order 91-17), § 173-175-140, filed
6/1/92, effective 7/2/92.]